Week 19 Daytona Repave Update: Paving of the racing surface complete
The finish line is in sight for the historic 2010 Daytona Repave. The paving crew from Lane Construction reached a milestone moment as the paving of all four layers of the racing surface on the 2.5-mile tri-oval is now complete.
Type Article
Week 13 Daytona Repave Update: Project Reaches The Halfway Mark
The historic Daytona Repave project has reached halfway point and the removal of asphalt in Turns 1 and 2 has begun.
Type Article
Week 7 Daytona Repave Update: Paving On Skid Pad Extension Begins
The massive 2010 Daytona Repave entered its seventh week as construction continued in many different areas throughout the historic Daytona International Speedway.
Type Article
Week 6 Daytona Repave Update: Tear Down Of Pit Road Begins
Workers on the historic Daytona Repave project hit pit road for the first time, but there was no pit stop for four tires and fuel.
Type Article
Week 4 Daytona Repave Update: Paving Begins On The Historic Tri-Oval
The paver crossed the start/finish line for the first time this week but work on the historic 2010 Daytona Repave project is far from finished.
Type Article
Crews Begin Work On Historic Repaving Project
Crews start work on the historic repaving project at Daytona International Speedway.
Type Article
Week 21, 22 Daytona Repave update: Final layer of asphalt put down on pit road
The paving crew from Lane Construction enjoyed the Thanksgiving holiday with their families and is now back at work wrapping up the final month of work repaving historic Daytona International Speedway.
Type Article
Week 20 Daytona Repave update: Superstretch work complete
Even though paving is complete on the racing surface of Daytona International Speedway’s 2.5-mile tri-oval, the paving crew from Lane Construction continues to be busy with work around the “World Center of Racing” during the 20th week of the Daytona Repave project.
Type Article
Week 18 Daytona Repave Update: Paving of the Final Layer in Turns 1 and 2
The process of putting down the fourth and final layer of asphalt in Turns 1 and 2 is ongoing during the 18th week of the repaving of Daytona International Speedway.
Type Article
Week 12 Daytona Repave Update: First Paving Of The Wearing Course Begins
The paving of the wearing course, the fourth and final layer of asphalt, was put down on the legendary 2.5-mile tri-oval of Daytona International Speedway for the first time during Week 12 of the Daytona Repave.